The parties to government procurement refer to the principal entities of all kinds that enjoy rights and undertake obligations in government procurement, including the procuring entities, the ()and the procuring agencies.
A.users
B.servers
C.producers
D.suppliers
您可能感興趣的試卷
- 2009年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2009年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2010年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2010年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2011年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2011年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2012年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師上半年上午試卷
你可能感興趣的試題
There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.
A.share
B.Mitigate
C.Transfer
D.Acceptance
A ()is a collection of projects and other work that are grouped together to facilitate effective management ofthat work to meet strategic business objectives.
A.program
B.portfolio
C.projectoflargesize
D.PMO
Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
A.Benchmarking
B.Quality metric
C.Quality checklist
D.Brainstornung
Contract closeout is a process that involves()
A.Customer satisfaction analysis and final payment
B.Administrative closeout and archiving records
C.Finial contractor payment and Lessons learned
D.Product verification and administrative closeout
最新試題
A ()is a collection of projects and other work that are grouped together to facilitate effective management ofthat work to meet strategic business objectives.
空白(3)處填()
In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()
Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().
空白(5)處填()
空白(1)處填()
An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?
空白(3)處填()
空白(2)處填()
The TCP protocolis a ()layer protocol.