單項(xiàng)選擇題

A customer is installing an HMC-managed Power 720 with two partitions, one for Production the other for Testing. They plan to use the Testing partition only occasionally and want to minimize hardware.
Which of the following meets these requirements?()

A.Create a system profile for each partition. Assign all needed resources as 'required'.
B.Define all system resources as 'desired' on the Testing partition. Activate only as needed.
C.Create two shared processor pools. Assign the minimal I/O resources required for each partition to the shared pools.
D.Create both partitions with minimal 'required' resources, and optional resources as 'desired'. Activate each partition as necessary.


您可能感興趣的試卷

你可能感興趣的試題

1.單項(xiàng)選擇題How can resource allocations for an active partition on a Power 750 be changed immediately and permanently?()

A.Use Capacity on Demand to add the resources.
B.Use DLPAR to add the resources and select the 'permanent' option.
C.Use DLPAR to add the resources, and change the partition profile.
D.Use an Operating System command to permanently request the resources.

2.單項(xiàng)選擇題Which of the following includes Active Memory Sharing (AMS)?()

A.PowerHA Enterprise Edition
B.PowerVM Enterprise Edition
C.VMControl Enterprise Edition
D.Systems Director Enterprise Edition

4.單項(xiàng)選擇題

A retail customer has an 8-core Power 740 server with 2 partitions. Production has 4 dedicated cores and the test partition has 2 dedicated cores. Both partitions run during the day without problems. At night, batch processing is exceeding the run window. 
Which solution addresses this problem without requiring additional hardware?()

A.Adding VMControl will automate processor resource allocation during peak workloads 
B.Enable Dynamic Symmetric Multithreading in the HMC to balance workloads across processors.
C.Add processing resources during the times they are required using Utility Capacity on Demand.
D.Changing the partitions to Uncapped can make use of additional processor cycles during peak workloads. 

5.單項(xiàng)選擇題

A customer has an HMC-managed Power Systems server with 6 partitions. Four production partitions are subject to varying workloads throughout the day, and two are used for development and testing. The production applications have different licensing limitations on the number of physical cores that may be used. The development partitions can use no more than 1 core. The customer would like to dynamically optimize processor utilization within the licensing limits, with minimal operator intervention. 
Which of the following meets the customer requirement?()

A.Define the production partitions' maximum CPU to the licensing limitations. Define the development/test partition maximums to one core. Configure each partition to be capped. 
B.Define the production partitions' maximum CPU to the licensing limitations. Define the development/test partition maximums to one core. Configure each partition to be uncapped. 
C.Define the production partitions' maximum CPU to the licensing limitations. Define the development/test partitions to use no more than one core. Configure the HMC scheduler to dynamically assign processors among the pools over a day. 
D.Create a shared processor pool for each production partition, with the maximum processor limit set to the licensing limit for the application in the pool. Assign the development and testing partitions to a processor pool with a maximum of 1 core. Configure each partition to use uncapped processing. 

最新試題

Which of the following has an integrated database?()

題型:?jiǎn)雾?xiàng)選擇題

A customer is implementing a POWER Blade solution which requires the VIO Server to be mirrored on internal disk drives. Which Blade supports the requirement?()

題型:?jiǎn)雾?xiàng)選擇題

A customer would like to configure an uncapped LPAR so that it can use 2 to 8 cores depending on the workload characteristics. With SMT4 enabled, what is the least amount of processing resources which can be configured for the LPAR?()

題型:?jiǎn)雾?xiàng)選擇題

A customer plans to consolidate two 8-core POWER6 systems with a total of 8 PCI-X adapters, 6 PCIe adapters, and a PCI-X I/O drawer into a 16-core Power 750.Which action allows the most efficient use of existing equipment?()

題型:?jiǎn)雾?xiàng)選擇題

A customer has 4 application and 2 database servers that will be installed in partitions on a Power 750. They are concerned that the database software vendor will charge based on every processor core in the server.Which action will reduce the potential vendor software costs?()

題型:?jiǎn)雾?xiàng)選擇題

An end user is deploying Blade servers to replace obsolete rack mounted servers. In addition to AIX Web server and database workloads, they also have Windows workloads.Which Blade is designed for Windows workloads?()

題型:?jiǎn)雾?xiàng)選擇題

A data center includes a Power 750 server running AIX and Linux, and PS700 Blades running AIX. What can the customer use to update AIX and Linux, create and deploy LPARs, and set energy caps for both servers from a single console?()

題型:?jiǎn)雾?xiàng)選擇題

A Power 720 customer using IVM wants to implement dual VIO servers, but is unable to create the second server. What is the most likely reason for this?()

題型:?jiǎn)雾?xiàng)選擇題

A customer plans to consolidate multiple business unit applications on a single Power Systems server. The maximum number of cores which can be used by each business unit must be limited by creating shared processor pools.What is the minimum PowerVM Edition which provides this feature?()

題型:?jiǎn)雾?xiàng)選擇題

A customer has a Power 750 with the following: One processor card with 8 cores enabled, and 64GB RAM installed One GX+ adapter with one I/O drawer attached; One 4-port 1Gbps IVE adapterPowerVM Standard Edition; They need to add a GX++ adapter and cable it to an I/O drawer.Which of the following must also be ordered?()

題型:?jiǎn)雾?xiàng)選擇題