The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
A.estimating
B.defining
C.planning
D.sequencing
您可能感興趣的試卷
- 2009年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2009年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2010年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2010年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2011年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2011年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2012年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
你可能感興趣的試題
A.project scope statement
B.project requirement
C.project charter
D.product specification
The()provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan
B.contract
C.project human resource plan
D.projectcharter
The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
A.Planning
B.Executing
C.Monitoring and Controlling
D.Closing
The()defines the phases that connect the beginning of a project to its end.
A.schedule
B.project life cycle
C.temporary
D.milestone
()means that every project has a definite beginning and a definite end.
A.Projectphase
B.Unique
C.Temporary
D.Closure
最新試題
The TCP protocolis a ()layer protocol.
空白(2)處填()
In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project's communication. According to Metcalfe's Law, a project with 10 stakeholders has()potential communication channels.
空白(1)處填()
空白(1)處填()
空白(3)處填()
You are working on the cost budget for one project. Which of the following is true()
Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.
An example of scope verification is ().
Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.