A company plans to deploy a two-enclosure, 23-core Power 780 system with AIX, IBM i and Linux in the following configuration: 3 AIX partitions with dedicated network and disk adapters; 1 native IBM i partition acting as a host; 1 hosted IBM i partition; 2 hosted Linux partitions.
Which configuration will provide boot disk capability to all partitions?()
A.Use dual-split backplane in both enclosures for the three AIX partitions and the IBM i partition.
B.Put each partition on a dedicated controller using the triple-split backplane option in both enclosures.
C.Use the triple-split backplane option in one enclosure for the AIX partitions, and the default dual-split backplane for the IBM i partition in the second enclosure.
D.Use the triple-split backplane option in one enclosure for the AIX partitions, and the non-split backplane mode in the second enclosure for the IBM i hosting partition.
您可能感興趣的試卷
你可能感興趣的試題
A.Configure 2 CFFh combination fibre channel / gigabit Ethernet adapters
B.Configure 1 CFFh 2-port fibre channel adapter and 1 CIOv 2-port gigabit Ethernet adapter
C.Configure 1 CIOv 2-port fibre channel adapter and 1 CFFh combination fibre channel / gigabit Ethernet adapter
D.Configure 1 CIOv 2-port gigabit Ethernet adapter and 1 CFFh combination fibre channel / gigabit Ethernet adapter
A.Before the first solution design meeting with the customer
B.After the solution design proposal is submitted to manufacturing for review
C.Once the customer has supplied the solution design specifications to the sales team
D.After the solution design is completed and before the proposal is submitted to the customer
A.Identify, assess, and mitigate technical risks.
B.Verify pricing and gather components for special bid submission.
C.Verify the proposed solution will fit within the customer's budget.
D.Review competitive offerings, system performance and delivery schedules.
Using the following information: Performance data from an existing system that a new system will replace; Performance estimates that anticipate future workloads; Micro-partitioning and logical partitioning implementations.
Which of the following allows a technical sales representative to create a system design which can be imported into an HMC?()
A.IBM eConfig
B.IBM Performance Monitor
C.IBM Workload Estimator (WLE)
D.IBM System Planning Tool (SPT)
A customer requires their application to have high availability within a data center, and also the ability to recover at a data center located 600km away in the event of an outage.
Which system software solution component supports the customer requirement?()
A.PowerHA SystemMirror Basic Edition
B.PowerHA SystemMirror Express Edition
C.PowerHA SystemMirror Standard Edition
D.PowerHA SystemMirror Enterprise Edition
最新試題
A customer wants to implement the following Blades in BladeCenter H:Two POWER Blades running IBM i partitions.Two POWER Blades running AIX and LinuxFour x86 Blades running Windows.Which of the following design consideration statements is correct?()
A customer requires their application to have high availability within a data center, and also the ability to recover at a data center located 600km away in the event of an outage.Which system software solution component supports the customer requirement?()
A customer wants to migrate their existing compute-intensive POWER6 570 to a Power 770. Which of their existing I/O adapters can be migrated to Power 770 enclosures?()
A customer has a Power 750 with the following: One processor card with 8 cores enabled, and 64GB RAM installed One GX+ adapter with one I/O drawer attached; One 4-port 1Gbps IVE adapterPowerVM Standard Edition; They need to add a GX++ adapter and cable it to an I/O drawer.Which of the following must also be ordered?()
An end user is deploying Blade servers to replace obsolete rack mounted servers. In addition to AIX Web server and database workloads, they also have Windows workloads.Which Blade is designed for Windows workloads?()
How can resource allocations for an active partition on a Power 750 be changed immediately and permanently?()
A customer has an LPAR with 4 dedicated cores on a POWER7 server with SMT4 enabled. How many logical processors are presented to an application running on this LPAR?()
A company plans to deploy a two-enclosure, 23-core Power 780 system with AIX, IBM i and Linux in thefollowing configuration: 3 AIX partitions with dedicated network and disk adapters; 1 native IBM i partition acting as a host1 hosted IBM i partition; 2 hosted Linux partitions.Which configuration will provide boot disk capability to all partitions?()
While using virtualization to share SAN adapters on a server, how does Node Port ID Virtualization (NPIV) differ from Virtual SCSI (vSCSI) related to the use of multipathing software?()
A POWER7 processor has L1, L2 and L3 caches. Which of the three caches uses embedded DRAM (eDRAM) technology?()