In project management, a ( )is a list of a project’s milestones, activities, and deliverables, usually with intended start and finish date. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events.
A. schedule
B. WBS
C. SOW
D. charter
( )can be considered as part of risk mitigation.
A. Risk identification
B. Purchasing insurance
C. Assessment of outcomes
D. Assessment of probabilities
( )is not the advantage of GERT (Graphical evaluation and review techniques)as compared with PERT (project evaluation and review techniques).
A. Allowing looping
B. Allowing for dummy tasks
C. Allowing branching
D. Allowing multiple project end results
最新試題
為了評(píng)估因趕工對(duì)項(xiàng)目可能造成的影響,項(xiàng)目經(jīng)理首先應(yīng)該計(jì)算:()
WBS是項(xiàng)目構(gòu)成單元的一個(gè)“產(chǎn)品導(dǎo)向”的構(gòu)架。WBS中的每一項(xiàng)一般都只有一個(gè)確定指標(biāo),這些指標(biāo)是:()
總歷時(shí)(totalduration)是多少?()
項(xiàng)目經(jīng)理、利害關(guān)系者和項(xiàng)目班子成員在整個(gè)項(xiàng)目階段都承擔(dān)著職責(zé)。作為項(xiàng)目經(jīng)理,你可以將項(xiàng)目范圍與項(xiàng)目的角色掛鉤,說明哪些活動(dòng)由哪些人參與,你可以用以下何種方式來描述這些信息。()
工作A悲觀估計(jì)需要36天完成,很有可能21天完成,樂觀估計(jì)只用6天完成,那么工作A從16天到26天之間完成的可能性是()
你是一家旅行用品公司的項(xiàng)目經(jīng)理。你公司準(zhǔn)備在即將推出的春季產(chǎn)品目錄中增加一款新產(chǎn)品線。你的項(xiàng)目組要用10個(gè)月的時(shí)間獲得供應(yīng)商的合同、確定設(shè)計(jì)方案、將產(chǎn)品加入產(chǎn)品目錄以及備貨。這是以下哪項(xiàng)所描述的例子?()
范圍核實(shí)將:()
你項(xiàng)目正處于質(zhì)量規(guī)劃過程。你知道,假如產(chǎn)品在組織控制期間沒滿足客戶的要求,就會(huì)導(dǎo)致糾正行動(dòng)、返工、廢品和停工。以下哪項(xiàng)是質(zhì)量成本的真實(shí)描述?()
可能影響項(xiàng)目小組的人員建設(shè)的一個(gè)制約因素:()
你是收款機(jī)系統(tǒng)的項(xiàng)目經(jīng)理,你公司為零售業(yè)生產(chǎn)收款和系統(tǒng)軟件。你客戶提出了一個(gè)改變收款機(jī)系統(tǒng)特征的變更要求。你運(yùn)用了綜合變更控制過程的哪個(gè)工具和技術(shù)來描述了收款機(jī)系統(tǒng)的特征?()