The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
A.estimating
B.defining
C.planning
D.sequencing
您可能感興趣的試卷
你可能感興趣的試題
The () describes, in detail, the project's deliverables and the work required to create those deliverables.
A.project scope statement
B.project requirement
C.project charter
D.product specification
A.project management plan
B.contract
C.project human resource plan
D.project charter
The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
A.Planning
B.Executing
C.Monitoring and Controlling
D.Closing
() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.
A.Project managers
B.Project team members
C.Sponsors
D.Project stakeholders
The() defines the phases that connect the beginning of a project to its end.
A.schedule
B.project life cycle
C.temporary
D.milestone
最新試題
The()provides the project manager with the authority to apply organizational resources to project activities.
The() defines the phases that connect the beginning of a project to its end.
The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.
空白(2)處應(yīng)選擇()
The inputs of developing project management plan do not include()
On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.
()from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.